Regional Airports Development Scheme

 Royalties for regions logo

Albany
Year: 1999
Project: Install Instrument Landing System (ILS)
Recipient: Southern Province Regional Development Organisation
RADS contribution: $200,000.00
Total project cost: $800,000.00
 
Year: 1995
Project: Construct terminal
Recipient: City of Albany
RADS contribution: $180,000.00
Total project cost: $1,135,000.00
 
Augusta
Year: 2005
Project: Construct and asphalt a helipad and construct a fuel storage facility
Recipient: Shire of Augusta-Margaret River
RADS contribution: $15,917.10
Total project cost: $31,951.00
 
Year: 2000
Project: Master plan and Runway upgrade
Recipient: Shire of Augusta-Margaret River
RADS contribution: $132,970.00
Total project cost: $182,901.40
 
Year: 1998
Project: Install pilot activated lighting
Recipient: Shire of Augusta-Margaret River
RADS contribution: $6,000.00
Total project cost: $8,175.00
Balgo
Year: 2007
Project: Improve the airport safety equipment and airport building
Recipient: Aspen Monkey Mia Pty Ltd
RADS contribution: $77,000.00
Total project cost: $154,545.44
 
Year: 2003
Project: Upgrade runways, improve fuel facilities and re-install fencing
Recipient: Burringurrah Aboriginal Community Incorporated
RADS contribution: $67,800.00
Total project cost: $180,000.00
 
Year: 2000
Project: Develop master plan
Recipient: Kimberley Development Commission
RADS contribution: $25,000.00
Total project cost: $35,000.00
Beacon
Year: 2001
Project: Runway upgrade
Recipient: Shire of Mt Marshall
RADS contribution: $14,000.00
Total project cost: $27,867.16
Beagle Bay
Year: 2000
Project: Install emergency lighting
Recipient: Kimberley Development Commission
RADS contribution: $25,000
Total project cost: $31,209
Bellburn
Year: 2004
Project: Upgrade the airstrip
Recipient: Department of Environment and Conservation
RADS contribution: $123,760.00
Total project cost: $1,035,671.00
Bidyadanga
Year: 2004
Project: Construct an aircraft parking, run-up and tie-down area
Recipient: Bidyadanga Aboriginal Community La Grange Inc.
RADS contribution: $17,100.00
Total project cost: $38,600.00
 
Year: 2003
Project: Refurbish the hangar
Recipient: Bidyadanga Aboriginal Community, Department of Housing and Works
RADS contribution: $9,436.00
Total project cost: $21,531.00
 
Year: 2001
Project: Install fixed lighting
Recipient: Bidyadanga Aboriginal Community, Department of Housing and Works
RADS contribution: $95,000.00
Total project cost: $115,000.00
 
Year: 2000
Project: Install pilot activated lighting
Recipient: Bidyadanga Aboriginal Community La Grange Inc.
RADS contribution: $20,000.00
Total project cost: $40,000.00
Billiluna  
Year: 2003
Project: Upgrade runway strip, replace markers, Upgrade lighting
Recipient: Mindibungu Aboriginal Corporation
RADS contribution: $71,250.00
Total project cost: $142,500.00
 
Year: 2000
Project: Install pilot activated lighting
Recipient: Mindibungu Aboriginal Corporation
RADS contribution: $11,296.00
Total project cost: $17,470.43
Blackstone
Year: 2001
Project: Install mains powered lighting
Recipient: Shire of Westonia
RADS contribution: $39,000.00
Total project cost: $78,000.00
Bremer Bay
Year: 2000
Project: Install pilot activated lighting
Recipient: Shire of Jerramungup
RADS contribution: $27,819.00
Total project cost: $52,150.00
 
Year: 1999
Project: Upgrade airstrip
Recipient: Shire of Jerramungup
RADS contribution: $134,250.00
Total project cost: $428,640.00
Brooklands
Year: 2005
Project: Seal both runways
Recipient: Skydive Express WA Pty Ltd
RADS contribution: $163,484.00
Total project cost: $327,484.00
Bruce Rock
Year: 2001
Project: Upgrade airstrip
Recipient: Shire of Bruce Rock
RADS contribution: $70,000.00
Total project cost: $235,938.00
Bunbury
Year: 2006
Project: Construct new taxiways
Recipient: City of Bunbury
RADS contribution: $170,000.00
Total project cost: $407,575.00
 
Year: 2004
Project: Install standby power
Recipient: City of Bunbury
RADS contribution: $14,948.50
Total project cost: $29,897.00
 
Year: 2001
Project: Construct vermin-proof fencing
Recipient: City of Bunbury
RADS contribution: $13,485.00
Total project cost: $29,927.15
 
Year: 1999
Project: Construct vermin-proof fencing
Recipient: City of Bunbury
RADS contribution: $3,978.85
Total project cost: $15,915.42
 
Year: 1998
Project: Seal remaining 500m of runway
Recipient: City of Bunbury
RADS contribution: $32,115.00
Total project cost: $68,330.00
Burringurrah
Year: 2007
Project: Seal runway
Recipient: Shire of Kellerberrin
RADS contribution: $181,000.00
Total project cost: $362,000.00
 
Year: 2004
Project: Upgrade the airstrip to RFDS requirements
Recipient: Burringurrah Aboriginal Community Incorporated
RADS contribution: $56,500.00
Total project cost: $113,000.00
Busselton
Year: 2007
Project: Construct animal fencing
Recipient: Shire of Busselton
RADS contribution: $55,000.00
Total project cost: $110,000.00
 
Year: 2001
Project: Approval & Application of CTAF at Busselton Airport and AFRU
Recipient: Shire of Busselton
RADS contribution: $1,285.91
Total project cost: $2,571.82
 
Year: 2000
Project: Install refuelling facility
Recipient: Shire of Busselton
RADS contribution: $46,000.00
Total project cost: $116,193.38
 
Year: 1996
Project: Construct new airport
Recipient: Shire of Busselton
RADS contribution: $3,500,000.00
Total project cost: $5,500,000.00
Carnarvon
Year: 2006
Project: Commission of a geotechnical survey on the existing runway
Recipient: Shire of Carnarvon
RADS contribution: $43,900.00
Total project cost: $87,590.00
 
Year: 2004
Project: Commission an airport master plan
Recipient: Shire of Carnarvon
RADS contribution: $15,000.00
Total project cost: $30,000.00
 
Year: 2003
Project: Upgrade airport lighting
Recipient: Shire of Carnarvon
RADS contribution: $68,210.00
Total project cost: $143,892.00
Cervantes
Year: 2001
Project: Install turn around areas and a hard stand
Recipient: Shire of Dandaragan
RADS contribution: $22,950.00
Total project cost: $57,869.03
Collie
Year: 2003
Project: Airport Perimeter Fencing
Recipient: Shire of Collie
RADS contribution: $21,500.00
Total project cost: $43,008.05
 
Year: 1999
Project: Seal apron, taxiway and thresholds of both runways
Recipient: Shire of Collie
RADS contribution: $13,000.00
Total project cost: $26,541.00
Coral Bay
Year: 2006
Project: Interim Upgrade (to CASA standards)
Recipient: Department for Planning and Infrastructure Aviation
RADS contribution: $200,000.00
Total project cost: $200,000.00
Corrigin
Year: 2001
Project: Install pilot activated lighting
Recipient: Shire of Corrigin
RADS contribution: $1,745.00
Total project cost: $3,538.90
Cue
Year: 2003
Project: Install pilot activated lights, automatic weather station and electronic kangaroo guard
Recipient: Shire of Cue
RADS contribution: $23,000.00
Total project cost: $47,920.00
Cunderdin
Year: 2206
Project: Construct a patient transfer facility
Recipient: Shire of Cunderdin
RADS contribution: $13,395.00
Total project cost: $27,870.00
 
Year: 1998
Project: Install pilot activated lighting
Recipient: Shire of Cunderdin
RADS contribution: $10,000.00
Total project cost: $14,984.00
Denmark
Year: 2003
Project: Upgrade, extend runway, install pilot activated lighting and fence the airport
Recipient: Shire of Denmark
RADS contribution: $199,781.00
Total project cost: $434,455.67
Derby
Year: 2007
Project: Construct animal fencing
Recipient: Aboriginal Affairs Department, Ministry for Housing and Aboriginal & Torres Straits Islander Commission
RADS contribution: $211,000.00
Total project cost: $504,405.00
 
Year: 1998
Project: Re-seal runway
Recipient: Shire of Derby-West Kimberley
RADS contribution: $500,000.00
Total project cost: $771,425.91
Djugerari
Year: 2005
Project: Relocate runway and aircraft parking area, install fencing, marking and wind sock
Recipient: Burringurrah Aboriginal Community Incorporated
RADS contribution: $104,000.00
Total project cost: $266,804.00
Dongara
Year: 2007
Project: Construct animal fencing
Recipient: Shire of Irwin
RADS contribution: $36,000.00
Total project cost: $73,633.00
 
Year: 2006
Project: Seal the runway and turning nodes and clear vegetation from approach areas
Recipient: Shire of Irwin
RADS contribution: $86,905.00
Total project cost: $204,436.50
 
Year: 2000
Project: Extend runway, install runway lighting
Recipient: Shire of Irwin
RADS contribution: $13,700.00
Total project cost: $40,700.00
Drysdale River
Year: 2001
Project: Extend runway, install runway lighting
Recipient: Drysdale River Station
RADS contribution: $9,155.55
Total project cost: $18,922.68
East Wallabi Island
Year: 2007
Project: Upgrade the runway
Recipient: Department of Fisheries
RADS contribution: $42,600.00
Total project cost: $85,302.73
Esperance
Year: 2006
Project: Asphalt overlay the taxiway and apron
Recipient: Shire of Esperance
RADS contribution: $136,485.00
Total project cost:  
 
Year: 2003
Project: Extend the runway
Recipient: Shire of Esperance
RADS contribution: $179,107.90
Total project cost: $778,730.00
 
Year: 2000
Project: Master plan
Recipient: Shire of Esperance
RADS contribution: $20,250.81
Total project cost: $22,659.00
Fitzroy Crossing
Year: 2005
Project: Bitumen resealing of the runway
Recipient: Shire of Derby-West Kimberley
RADS contribution: $137,850.00
Total project cost: $297,299.68
 
Year: 2000
Project: Install pilot activated lighting
Recipient: Shire of Derby-West Kimberley
RADS contribution: $34,590.00
Total project cost: $114,277.82
 
Year: 1996
Project: Seal runway
Recipient: Shire of Derby-West Kimberley
RADS contribution: $1,000,000.00
Total project cost: $1,000,000.00
Forrest
Year: 1998
Project: Install power generators
Recipient: Fayburn Pty Ltd
RADS contribution: $35,102.00
Total project cost: $50,873.00
Gascoyne Junction
Year: 2004
Project: Install animal proof fencing
Recipient: Shire of Upper Gascoyne
RADS contribution: $26,255.61
Total project cost: $52,511.21
 
Year: 1999
Project: Seal runway
Recipient: Shire of Upper Gascoyne
RADS contribution: $150,000.00
Total project cost: $295,000.00
Geraldton
Year: 2007
Project: Replace standby power generator system
Recipient: Shire of Greenough
RADS contribution: $41,000.00
Total project cost: $164,580.00
 
Year: 2005
Project: Asphalt and line mark runway 14/32
Recipient: Shire of Greenough
RADS contribution: $120,000.00
Total project cost: $428,678.61
 
Year: 2000
Project: Construct new airport terminal
Recipient: Shire of Greenough
RADS contribution: $250,000.00
Total project cost: $3,600,000.00
 
Year: 1998
Project: Re-seal runway
Recipient: Shire of Greenough
RADS contribution: $400,000.00
Total project cost: $2,000,000.00
Gnaraloo Station
Year: 2007
Project: Extend the runway, construct turnaround areas, apron and taxiway and install markers, windsock and lighting
Recipient: Shire of Morawa
RADS contribution: $57,000.00
Total project cost: $114,400.00
Gnowangerup
Year: 2007
Project: Seal the runway and construct a patient transfer facility
Recipient: Southern Province Regional Development Organisation
RADS contribution: $54,000.00
Total project cost: $216,121.00
 
Year: 2003
Project: Erect animal fencing
Recipient: Shire of Gnowangerup
RADS contribution: $16,833.11
Total project cost: $33,666.22
 
Year: 2000
Project: Re-seal apron
Recipient: Shire of Gnowangerup
RADS contribution: $17,500.00
Total project cost: $35,000.00
 
Year: 1998
Project: Install pilot activated lighting
Recipient: Shire of Gnowangerup
RADS contribution: $4,500.00
Total project cost: $6,350.00
Halls Creek
Year: 2005
Project: Improve sight lines between the two runways
Recipient: Shire of Halls Creek
RADS contribution: $10,039.75
Total project cost: $20,079.51
 
Year: 2004
Project: Install animal proof fencing
Recipient: Shire of Halls Creek
RADS contribution: $60,000.00
Total project cost: $323,850.69
 
Year: 1996
Project: Seal runway, install pilot activated lighting
Recipient: Shire of Halls Creek
RADS contribution: $1,000,000.00
Total project cost: $1,000,000.00
Home Valley
Year: 2005
Project: Upgrade the runway, taxiway and apron
Recipient: Indigenous Land Corporation
RADS contribution: $77,615.00
Total project cost: $250,992.00
Jerramungup
Year: 2000
Project: Seal hardstand & taxiway, upgrade main runway markers
Recipient: Shire of Jerramungup
RADS contribution: $9,100.00
Total project cost: $18,200.00
Jigalong
Year: 2004
Project: Widen the airstrip and upgrade the lighting
Recipient: Burringurrah Aboriginal Community Incorporated
RADS contribution: $171,940.00
Total project cost: $343,890.00
 
Year: 2003
Project: Install pilot activated ,solar powered lighting
Recipient: Western Desert Puntukurnuparna Aboriginal Corporation
RADS contribution: $23,380.00
Total project cost: $54,200.00
Jurien Bay
Year: 2004
Project: Seal the runway, install runway lighting and fencing
Recipient: Shire of Dandaragan
RADS contribution: $130,000.00
Total project cost: $383,824.00
 
Year: 1998
Project: Construct hardstand area
Recipient: Shire of Dandaragan
RADS contribution: $8,250.00
Total project cost: $16,440.00
Kadjina
Year: 2004
Project: Upgrade the airstrip to RFDS requirements
Recipient: Burringurrah Aboriginal Community Incorporated
RADS contribution: $131,150.00
Total project cost: $262,300.00
Kalbarri
Year: 1999
Project: Construct new airport
Recipient: Shires of Greenough and Northampton
RADS contribution: $924,000.00
Total project cost: $1,400,000.00
Kalumburu
Year: 2001
Project: Aerodrome upgrade and Pilot Activated Lighting
Recipient: Burringurrah Aboriginal Community Incorporated
RADS contribution: $250,000.00
Total project cost: $570,000.00
Karijini
Year: 2001
Project: Upgrade Karijini Airstrip
Recipient: Department of Environment and Conservation
RADS contribution: $95,450.00
Total project cost: $190,900.00
Katanning
Year: 2004
Project: Install cross strip runway lights and connect to the existing PAL system
Recipient: Shire of Katanning
RADS contribution: $23,820.00
Total project cost: $47,652.00
 
Year: 2003
Project: Erect animal fencing and upgrade the cross-runway
Recipient: Town of Port Hedland
RADS contribution: $35,023.00
Total project cost: $109,763.22
 
Year: 1999
Project: Seal apron and install lighting,
Recipient: Shire of Katanning
RADS contribution: $15,903.00
Total project cost: $37,493.38
Kellerberrin
Year: 2006
Project: Seal the taxiway and aircraft parking area
Recipient: Shire of Kellerberrin
RADS contribution: $17,055.00
Total project cost: $34,110.00
 
Year: 2001
Project: Widen landing strip
Recipient: Shire of Kellerberrin
RADS contribution: $39,645.00
Total project cost: $80,094.49
Kojonup
Year: 1998
Project: Seal runway thresholds, taxiway & hardstand
Recipient: Shire of Kojonup
RADS contribution: $14,080.00
Total project cost: $29,486.28
Kondinin
Year: 2004
Project: Construct a patient transfer shed, sealed run-up area and extend the runway to RFDS requirements and upgrade the lighting with PAL
Recipient: Shire of Kondinin
RADS contribution: $60,200.00
Total project cost: $178,000.00
Kulin
Year: 2004
Project: Extend the runway and upgrade the markings
Recipient: Shire of Kulin
RADS contribution: $16,784.15
Total project cost: $33,568.30
Kunawarritji
Year: 2003
Project: Erect a fuel shed
Recipient: Western Desert Puntukurnuparna Aboriginal Corporation
RADS contribution: $3,960.00
Total project cost: $8,160.00
 
Year: 2000
Project: $8,160.00
Recipient: Kunawarritji Aboriginal Community
RADS contribution: $20,000.00
Total project cost: $40,000.00
Kununoppin
Year: 2006
Project: Seal runway and taxiway to parking area
Recipient: Shire of Trayning
RADS contribution: $72,564.00
Total project cost: $152,606.00
Kununurra
Year: 2004
Project: Reseal and remark the runway and taxiways
Recipient: Shire of Wyndham - East Kimberley
RADS contribution: $55,511.76
Total project cost: $252,326.19
Kupartiya
Year: 2005
Project: install aircraft parking area and boundary fencing
Recipient: Burringurrah Aboriginal Community Incorporated
RADS contribution: $18,800.00
Total project cost: $37,600.00
 
Year: 2003
Project: Upgrade the runway and aircraft parking area
Recipient: Burringurrah Aboriginal Community Incorporated
RADS contribution: $39,825.00
Total project cost: $39,825.00
Lake Grace
Year: 2005
Project: Sealing and line marking the runway, re-sealing and upgrading the patient transfer area
Recipient: Shire of Lake Grace
RADS contribution: $32,249.00
Total project cost: $73,871.75
 
Year: 2004
Project: Install kangaroo proof fencing
Recipient: Shire of Lake Grace
RADS contribution: $12,971.06
Total project cost: $25,942.13
 
Year: 2003
Project: Seal the runway ends
Recipient: Shire of Lake Grace
RADS contribution: $3,481.70
Total project cost: $5,803.52
 
Year: 1999
Project: Install pilot activated lighting
Recipient: Shire of Lake Grace
RADS contribution: $10,904.00
Total project cost: $25,358.14
Laverton
Year: 2003
Project: Erect vermin proof fencing
Recipient: Shire of Laverton
RADS contribution: $49,071.00
Total project cost: $107,529.00
 
Year: 1998
Project: Extend apron, widen taxiway
Recipient: Shire of Laverton
RADS contribution: $30,000.00
Total project cost: $77,541.23
 
Learmonth
Year: 2004
Project: Purchase and installation of an explosives and narcotics detection unit
Recipient: Shire of Exmouth
RADS contribution: $72,000.00
Total project cost: $72,300.00
 
Year: 1998
Project: Upgrade & extend apron & taxiway
Recipient: Shire of Exmouth
RADS contribution: $500,000.00
Total project cost: $5,200,000.00
Leonora
Year: 2000
Project: Seal runway & apron, install runway lighting
Recipient: Shire of Leonora
RADS contribution: $185,000.00
Total project cost: $1,400,000.00
 
Year: 1999
Project: Extend the runway and the runway lighting
Recipient: Shire of Leonora
RADS contribution: $150,000.00
Total project cost: $375,000.00
Lombadina/Dampier Peninsula
Year: 1998
Project: Seal airstrip
Recipient: Aboriginal Affairs Department, Ministry for Housing and Aboriginal & Torres Straits Islander Commission
RADS contribution: $250,000.00
Total project cost: $800,000.00
Louisa Downs
Year: 2005
Project: Construction of airport
Recipient: Burringurrah Aboriginal Community Incorporated
RADS contribution: $104,000.00
Total project cost: $244,320.30
Manjimup
Year: 2003
Project: Extend the aircraft parking apron
Recipient: Shire of Manjimup
RADS contribution: $20,000.00
Total project cost: $65,911.47
 
Year: 2000
Project: Develop master plan, seal aircraft parking area
Recipient: Shire of Manjimup
RADS contribution: $7,660.00
Total project cost: $12,810.80
 
Year: 1997
Project: Install Non-Directional Beacon (NDB)
Recipient: Shire of Manjimup
RADS contribution: $250,000.00
Total project cost: $250,000.00
 
Year: 1997
Project: Widen runway
Recipient: Shire of Manjimup
RADS contribution: $20,000.00
Total project cost: $99,750.00
Marble Bar
Year: 2005
Project: Install pilot activated lighting
Recipient: Shire of East Pilbara
RADS contribution: $78,617.00
Total project cost: $157,456.98
Margaret River
Year: 1999
Project: Construct and seal second taxiway and apron and install a terminal
building
Recipient: Shire of Augusta-Margaret River
RADS contribution: $32,000.00
Total project cost: $38,022.88
 
Year: 1999
Project: Extend apron, widen runway seal
Recipient: Shire of Augusta-Margaret River
RADS contribution: $46,516.00
Total project cost: $68,406.34
 
Year: 1997
Project: Seal airstrip
Recipient: Shire of Augusta-Margaret River
RADS contribution: $33,489.00
Total project cost: $58,618.39
 
Year: 1996
Project: Install pilot activated lighting
Recipient: Shire of Augusta-Margaret River
RADS contribution: $30,000.00
Total project cost: $60,293.06
Marion Downs
Year: 2005
Project: Relocate airstrip
Recipient: Marion Downs Station
RADS contribution: $25,730.00
Total project cost: $51,459.00
Meekatharra
Year: 2005
Project: Install a pilot activated lighting control, aerodrome frequency response unit and replace damaged runway markers
Recipient: Shire of Meekatharra
RADS contribution: $5,881.95
Total project cost: $11,763.90
 
Year: 2003
Project: Reseal and mark aprons, replace markers and purchase radios
Recipient: Shire of Meekatharra
RADS contribution: $37,992.00
Total project cost: $77,448.84
Merredin
Year: 2004
Project: Construct aircraft hangars and improve runway condition
Recipient: China Southern Western Australian Flying College
RADS contribution: $125,000.00
Total project cost: $336,064.00
 
Year: 2003
Project: Upgrade the secondary runway
Recipient: China Southern Western Australian Flying College
RADS contribution: $36,750.00
Total project cost: $76,400.00
 
Year: 2001
Project: Construct patient transfer facility
Recipient: China Southern Western Australian Flying College
RADS contribution: $5,500.00
Total project cost: $19,309.41
Moora
Year: 2003
Project: Create a Master Plan for a new airstrip
Recipient: Shire of Moora
RADS contribution: $6,750.00
Total project cost: $13,500.00
Morawa
Year: 2006
Project: Construct turning nodes
Recipient: Shire of Morawa
RADS contribution: $36,123.00
Total project cost: $71,980.00
 
Year: 2004
Project: Install pilot activation system for the runway lighting
Recipient: Shire of Morawa
RADS contribution: $4,163.00
Total project cost: $8,326.00
 
Year: 2003
Project: Carry out repairs to the airstrip and salinity alleviation work
Recipient: Shire of Morawa
RADS contribution: $21,900.00
Total project cost: $44,581.00
 
Year: 1999
Project: Gravel & re-sheet main runway
Recipient: Shire of Morawa
RADS contribution: $5,000.00
Total project cost: $12,081.00
Mt Elizabeth
Year: 2003
Project: Upgrade the airstrip
Recipient: Mt Elizabeth Station
RADS contribution: $69,027.00
Total project cost: $147,528.00
Mt Hart
Year: 2005
Project: Widen the runway to 90m, improve the splay areas, construct a taxi way and install cone markers
Recipient: Department of Environment and Conservation
RADS contribution: $15,200.77
Total project cost: $30,401.57
 
Year: 2004
Project: Upgrade the runway to RFDS requirements
Recipient: Department of Environment and Conservation
RADS contribution: $68,800.00
Total project cost: $140,000.00
Mt House Station
Year: 2003
Project: Upgrade the airstrip
Recipient: Mt House Pastoral Partnership
RADS contribution: $58,750.00
Total project cost: $117,500.00
Mt Magnet
Year: 2003
Project: Seal mark and fence the runway
Recipient: Shire of Mount Magnet
RADS contribution: $187,533.76
Total project cost: $375,067.49
 
Year: 2000
Project: Seal runway
Recipient: Shire of Mount Magnet
RADS contribution: $250,000.00
Total project cost: $505,984.00
 
Year: 1999
Project: Install beep back radio unit (safety aid), re-seal apron
Recipient: Shire of Mount Magnet
RADS contribution: $16,883.00
Total project cost: $43,000.00
Mugarinya
Year: 2003
Project: Reconstruct and fence the airstrip and re-sheet the aircraft parking apron
Recipient: Burringurrah Aboriginal Community Incorporated
RADS contribution: $200,000.00
Total project cost: $400,000.00
Mukinbudin
Year: 2005
Project: Install vermin proof fencing
Recipient: Shire of Mukinbudin
RADS contribution: $43,000
Total project cost: $87,296
 
Year: 2003
Project: Upgrade the airstrip surface
Recipient: Shire of Mukinbudin
RADS contribution: $25,000.00
Total project cost: $60,264.06
Mulan
Year: 2007
Project: Install Pilot Activated Lighting and floodlights for the windsock and apron
Recipient: Mulan Aboriginal Corporation
RADS contribution: $113,000.00
Total project cost: $227,272.72
 
Year: 2000
Project: Install airstrip lighting, apron lighting & windsock
Recipient: Mulan Aboriginal Corporation
RADS contribution: $46,461.00
Total project cost: $106,593.54
Munjina/Auski
Year: 1996
Project: Construct airstrip
Recipient: Munjina
RADS contribution: $250,000.00
Total project cost: $250,000.00
Murchison
Year: 2004
Project: Upgrade the airstrip, construct runway turning nodes, a parking area and remarking
Recipient: Shire of Murchison
RADS contribution: $28,000.00
Total project cost: $74,061.34
Murrayfield
Year: 2007
Project: Extend taxiway 05/23
Recipient: Shire of Esperance
RADS contribution: $72,000.00
Total project cost: $144,626.00
 
Year: 1999
Project: Seal runway, install pilot activated lighting
Recipient: Royal Aero Club of Western Australia
RADS contribution: $200,000.00
Total project cost: $250,000.00
Nannup
Year: 2001
Project: Upgrade runway to RFDS standards
Recipient: Department of Environment and Conservation
RADS contribution: $24,000.00
Total project cost: $64,470.00
Nanutarra
Year: 1997
Project: Construct emergency landing area on North West Coastal Hwy
Recipient: Main Roads Western Australia
RADS contribution: $200,000.00
Total project cost: $200,000.00
Narembeen
Year: 2006
Project: Resurface existing runway and taxiway, install new taxiway and extend current runway
Recipient: Shire of Carnarvon
RADS contribution: $29,933.00
Total project cost: $67,613.00
Narrogin
Year: 2004
Project: Improve the drainage, upgrade the runway marking and the boundary fencing
Recipient: Town of Narrogin
RADS contribution: $10,170.34
Total project cost: $21,293.00
 
Year: 2003
Project: Upgrade pilot activated lights, sealed taxiway and aircraft parking
Recipient: Town of Narrogin
RADS contribution: $6,525.50
Total project cost: $13,051.00
 
Year: 2000
Project: Master plan
Recipient: Town of Narrogin
RADS contribution: $4,000.00
Total project cost: $8,987.00
 
Year: 1999
Project: Seal runway
Recipient: Town of Narrogin
RADS contribution: $46,000.00
Total project cost: $140,265.47
Newman
Year: 2006
Project: Construct new terminal
Recipient: Shire of East Pilbara
RADS contribution: $2,000,000.00
Total project cost: $9,800,000.00
 
Year: 2004
Project: Part 2 design a new passenger terminal
Recipient: Shire of East Pilbara
RADS contribution: $75,000.00
Total project cost: $150,000.00
 
Year: 2004
Project: Upgrade the airport
Recipient: Shire of East Pilbara
RADS contribution: $144,400.00
Total project cost: $777,102.36
 
Year: 2003
Project: Part 1 design a new passenger terminal
Recipient: Shire of East Pilbara
RADS contribution: $100,000.00
Total project cost: $242,753.26
Norseman
Year: 2004
Project: Develop an airport masterplan
Recipient: Shire of Dundas
RADS contribution: $3,750.00
Total project cost: $7,500.00
Northam
Year: 2005
Project: Apply a second seal and construct a new taxiway
Recipient: Shire of Boyup Brook
RADS contribution: $103,052.00
Total project cost: $206,105.00
 
Year: 2005
Project: Commission an airport master plan
Recipient: Town of Northam
RADS contribution: $6,600.00
Total project cost: $21,600.00
 
Year: 2000
Project: Seal runway
Recipient: Northam Aero Club
RADS contribution: $82,100.00
Total project cost: $163,928.00
Nugadong
Year: 2007
Project: Widen the runway, construct turnaround area and patient transfer facility and install lighting and fencing
Recipient: Shire of Dalwallinu
RADS contribution: $120,000.00
Total project cost: $464,000.00
 
Year: 1998
Project: Runway seal
Recipient: Shire of Dalwallinu
RADS contribution: $25,458.02
Total project cost: $25,458.02
Nullagine
Year: 2007
Project: Construct patient transfer and waiting facility with a public toilet
Recipient: Shire of East Pilbara
RADS contribution: $40,000.00
Total project cost: $80,000.00
One Arm Point
Year: 2006
Project: Upgrade the airport to Aircraft Landing Area (ALA) standards
Recipient: Burringurrah Aboriginal Community Incorporated
RADS contribution: $75,500.00
Total project cost: $153,800.00
Onslow
Year: 2004
Project: Extend and seal runway 03/21
Recipient: Department of Fisheries
RADS contribution: $174,240.00
Total project cost: $695,228.00
 
Year: 2000
Project: Construct runway, install pilot activated lighting
Recipient: Shire of Ashburton
RADS contribution: $890,000.00
Total project cost: $1,675,000.00
Oombulgurri
Year: 2000
Project: Re-sheet & upgrade runway, strip, taxiway & apron, drainage works
Recipient: Aboriginal Housing, Department of Housing and Works
RADS contribution: $213,300.00
Total project cost: $438,640.69
Parnngurr
Year: 2003
Project: Erect a fuel shed and install pilot activated, solar powered lighting
Recipient: Western Desert Puntukurnuparna Aboriginal Corporation
RADS contribution: $27,340.00
Total project cost: $62,360.00
 
Year: 2000
Project: Installation of emergency lighting, airport fencing, fuel storage shed and windsock
Recipient: Western Desert Puntukurnuparna Aboriginal Corporation
RADS contribution: $15,790.23
Total project cost: $31,580.46
Perenjori
Year: 2000
Project: Install beacon for pilot activated lighting
Recipient: Shire of Perenjori
RADS contribution: $5,000.00
Total project cost: $14,625.00
Port Hedland
Year: 2007
Project: Install runway and apron lighting and Precision Approach Path Indicator, extend Runway End Safety Area and develop airport master
Recipient: Town of Port Hedland
RADS contribution: $400,000.00
Total project cost: $1,017,545.46
 
Year: 1999
Project: Re-seal aprons, construct turning nodes on runway
Recipient: Town of Port Hedland
RADS contribution: $272,079.66
Total project cost: $630,000.00
Punmu
Year: 2003
Project: Erect a fuel shed, install pilot activated, mains powered lighting
Recipient: Western Desert Puntukurnuparna Aboriginal Corporation
RADS contribution: $19,960.00
Total project cost: $44,160.00
 
Year: 2000
Project: Installation of emergency lighting, airport fencing, fuel storage shed and windsock
Recipient: Western Desert Puntukurnuparna Aboriginal Corporation
RADS contribution: $15,790.23
Total project cost: $31,580.46
Ravensthorpe
Year: 2001
Project: Construction of a new aerodrome
Recipient: Coral Bay FESA Unit/Department for Planning and Infrastructure
RADS contribution: $350,000.00
Total project cost: $3,600,000.00
Sandfire
Year: 1999
Project: Re-sheet runway
Recipient: Sandfire Roadhouse
RADS contribution: $50,000.00
Total project cost: $50,000.00
Shark Bay
Year: 2006
Project: Install Perimeter Fencing (Animal Proof Fencing)
Recipient: Aspen Monkey Mia Pty Ltd
RADS contribution: $50,000.00
Total project cost: $100,000.00
 
Year: 2003
Project: Install pilot activated runway lights
Recipient: Shark Bay Airport Pty Ltd
RADS contribution: $85,829.50
Total project cost: $123,864.50
Silent Grove
Year: 2003
Project: Upgrade the airstrip to RFDS standard
Recipient: Department of Environment and Conservation
RADS contribution: $12,825.00
Total project cost: $30,401.57
Southern Cross
Year: 2003
Project: Replace runway turning node and provide uninterruptible power supply to runway lights
Recipient: Shire of Yilgarn
RADS contribution: $13,594.67
Total project cost: $27,189.34
Tjukayirla
Year: 2000
Project: Purchase of emergency lighting trailer
Recipient: Shire of Laverton
RADS contribution: $5,375.00
Total project cost: $10,819.00
 
Year: 1999
Project: Construct RFDS emergency landing area on Great Central Road
Recipient: Shire of Laverton
RADS contribution: $75,000.00
Total project cost: $285,406.25
Tjuntjuntjara
Year: 2004
Project: Rework the airstrip, remark and provide a windsock
Recipient: Burringurrah Aboriginal Community Incorporated
RADS contribution: $106,000.00
Total project cost: $212,000.00
Turkey Creek
Year: 2005
Project: Extend runway 21 by 200m, grade runway strip to 90m, remove vegetation from obstacle surface, install wind indicator, install marker
Recipient: Burringurrah Aboriginal Community Incorporated
RADS contribution: $54,500.00
Total project cost: $110,970.00
Varley
Year: 2003
Project: Install markers
Recipient: Shire of Kulin
RADS contribution: $2,146.00
Total project cost: $4,292.00
Wagin
Year: 2004
Project: Install airstrip fencing
Recipient: Shire of Wagin
RADS contribution: $23,302.94
Total project cost: $46,605.88
 
Year: 1999
Project: Upgrade main & cross runways
Recipient: Shire of Wagin
RADS contribution: $20,000.00
Total project cost: $85,236.00
Walpole
Year: 2003
Project: Upgrade the airstrip
Recipient: Department of Environment and Conservation
RADS contribution: $21,975.00
Total project cost: $73,987.00
Warburton
Year: 2001
Project: Seal airstrip and install pilot activated lighting
Recipient: Shire of Ngaanyatjarraku, Aboriginal and Torres Strait Islander Commission
RADS contribution: $300,000.00
Total project cost: $863,204.11
Wave Rock
Year: 1997
Project: Construct new airport
Recipient: Wave Rock Development Pty Ltd
RADS contribution: $308,000.00
Total project cost: $627,700.00
Wiluna
Year: 1996
Project: Seal runway
Recipient: Shire of Wiluna/Wiluna Gold
RADS contribution: $300,000.00
Total project cost: $845,000.00
Windidda
Year: 2003
Project: Erect a fuel shed and install solar powered pilot activated runway lights
Recipient: Western Desert Puntukurnuparna Aboriginal Corporation
RADS contribution: $27,340.00
Total project cost: $51,540.00
Windjana Gorge
Year: 2006
Project: Widen the runway and clear approach and take-off areas
Recipient: Department of Environment and Conservation
RADS contribution: $1,239.70
Total project cost: $2,479.40
Wongan Hills
Year: 2003
Project: Reconstruct and seal the runway and upgrade the lighting
Recipient: Shire of Wongan-Ballidu
RADS contribution: $209,375.00
Total project cost: $451,889.58
 
Year: 1998
Project: Seal apron
Recipient: Shire of Wongan-Ballidu
RADS contribution: $7,400.00
Total project cost: $8,344.80
Wyalkatchem
Year: 2006
Project: Construct a patient transfer facility
Recipient: Shire of Wyalkatchem
RADS contribution: $35,000.00
Total project cost: $79,241.00
 
Year: 2003
Project: Runway upgrade with final seal
Recipient: Shire of Wyalkatchem
RADS contribution: $9,744.93
Total project cost: $20,301.94
 
Year: 2000
Project: Upgrade, extend & seal runway, install emergency lighting
Recipient: Shire of Wyalkatchem
RADS contribution: $85,000.00
Total project cost: $278,359.98
Wyndham
Year: 2004
Project: Upgrade the airport lighting
Recipient: Shire of Wyndham - East Kimberley
RADS contribution: $10,567.00
Total project cost: $42,268.00
 
Year: 2000
Project: Install solar power warning lights
Recipient: Shire of Wyndham - East Kimberley
RADS contribution: $32,000.00
Total project cost: $65,340.00
 
Year: 1998
Project: Upgrade and seal runway
Recipient: Shire of Wyndham - East Kimberley
RADS contribution: $100,000.00
Total project cost: $580,000.00