Outer harbour

5. Plan now for the Outer Harbour at Kwinana

Aim: A new port will take much of the growth in traffic from Fremantle Port.

Highlights

Strategic assessment guidelines

  • A new Outer Harbour container port overflow facility will handle future trade beyond the capacity of the Inner Harbour. A draft of Assessment Guidelines, which will identify vision, goals, indicators and measures linked to key issues, is currently being finalised with public comments received.

  • Reporting on the strategic assessment of social, economic and environmental factors was programmed to start end of June 2005 and take six months. Assessment of integrated strategic reports and submissions by EPA (S16e) and WAPC will follow the reporting. Expected project completion date – Strategic Assessment Phase – finish in the first half of 2006, and Statutory Approvals Phase – 2007-08.

Rowley Road and Anketell Road

  • Planning concepts and reservation plans have been completed for the future extension of Rowley Road west from Kwinana Freeway and for a future freight rail link west from the standard gauge freight line to the northern end of the Kwinana/Naval Base industrial area and the Outer Harbour offshore northern access port options. A Planning Control Area has been gazetted to protect the road and rail corridor pending inclusion of the road and rail reservations in the Metropolitan Region Scheme.

  • Planning concepts and alignment options have also been prepared along Anketell Road for improved road and rail access to the southern access Outer Harbour Offshore and Onshore Port options and the central Naval Base/Kwinana industrial area west of Kwinana Freeway. A Planning Control Area has been gazetted to protect this corridor.

  • The Rowley Road and Anketell Road freight corridor concepts will be assessed as part of the broader Outer Harbour planning study, and preferred freight corridor concepts will be adopted through that process.

  • Guidelines are being prepared for appropriate land use and access to land abutting the proposed strategic road and rail access corridors, Rowley Road and Anketell Road.

  • A working group involving the Department for Planning and Infrastructure, Fremantle Ports, LandCorp and the Public Transport Authority will examine the issues surrounding future intermodal facilities in the Kwinana area. This work will take place over the next six to twelve months.

Thomas Road

  • Thomas Road is constructed to a four lane divided road standard. Preliminary investigations indicate that extension of Thomas Road west of Rockingham Road is not viable, therefore no further planning investigations or upgrading are proposed for Thomas Road.

Progress report

Strategic Planning for the Outer Harbour

Start

End

Status

Establish project working group (DPI/FPA)

Jun 2002

Sep 2002

Completed

Establish Steering Committee

Sep 2002

Mar 2003

Completed

Define the study area (based on outcomes of previous extensive land use, transport and port planning work)

Dec 2002

Sep 2003

Completed

Formulate/evaluate a preferred project implementation strategy (including community/stakeholder consultation and sustainability assessment); determine methodology for environmental, social and economic assessment

Jan 2003

May 2005

Completed

Seek Steering Committee endorsement of proposed project implementation strategy and study area

Mar 2003

Dec 2003

Completed


Detailed Implementation Planning for the Outer Harbour

Start

End

Status

Literature search of previous port planning reports and studies

Oct 2002

Mar 2003

Completed

Literature search of documented key issues

Sep 2002

Jun 2003

Completed

Identify key barriers to project approval and opportunities to address problems

Dec 2002

Feb 2003

Completed

Identify key stakeholders

Dec 2002

Dec 2003

Completed

Complete development of detailed project implementation strategy (as described above)

Dec 2003

May 2005

Completed


Rowley, Anketell and Thomas Roads

Start

End

Status

Rowley Road – develop options and agree preferred road and rail alignments

Sep 2002

Dec 2002

Completed

Rowley Road – define reservation for preferred road and rail alignments

Dec 2002

Jun 2003

Completed

Anketell Road – develop road and rail alignment options for input to Outer Harbour Port Planning Study

Mar 2003

Feb 2004

Completed

Anketell Road – define reservations for preferred road or rail alignments west of Rockingham Road (subject to outcome of Outer Harbour Port Planning Study)

To be developed

To be developed



 Find out more

Visual interpretation of the Outer Harbour planning project


Department of Transport