Planning and design has commenced for the $6 million upgrade of facilities at Two Rocks Marina with priority repairs to the breakwater now completed.

Stakeholder and community engagement has begun to look at the long-term vision for the facility with the Two Rocks Marina Reference Group holding its inaugural meeting on 4 April 2018.

  Project status

Two Rocks Marina will receive a $6 million revamp over the next two years to improve ageing infrastructure and prepare the facility for future needs. Improvements are designed to address ageing infrastructure, improve safety and provide a foundation for future redevelopment opportunities.

The Department of Transport, which took on the management of the facility in 2014 following the expiry of a lease with a private operator, will use the funding to improve access and infrastructure over the next two years.

This latest upgrade follows on from the June 2016 completion of a ramp upgrade and new boat pontoon, which was delivered as a result of consultation with the local community and City of Wanneroo.

The first major works - the Western Breakwater Repairs - have now been complete (May 2018). Approximately 7,000 tonnes of limestone was placed during the works which were designed to increase the breakwater's resilience to future storm events and improve public safety. The works also improve access for recreational fishing. Images of the works can be found in the image gallery below.

Works associated with the demolition and replacement of marine structure has also recently commenced with mobilisation of equipment late June 2018. A contractor area has been established between the boat ramp and the yacht club and during demolition and construction some materials will be ferried using a barge operating from the southern boat ramp.

Whilst there maybe be some impacts to the boat ramp users from time to time during load out of materials these will be kept to a minimum. The boat launching facility will remain open.

In addition to the immediate upgrade works, stakeholder and community engagement has begun through an information session and a Reference Group that will look at the long-term vision for the facility, with a view to creating local jobs. The Reference Group held its first meeting on 4 April 2018.

External Link 04/04/2018: New group to shape future of Two Rocks Marina
Opens in a new window 14/09/2017: Upgrade planned for Two Rocks Marina

  Project overview

The $6 million Two Rocks Marina upgrade is required to bring the run-down facility up to the standard expected by the community. The development is critical to deliver safety and access improvements and the works will include:

  • Demolition of condemned maritime structures, including the original fuel jetty;
  • Construction of relocated boat pens;
  • Upgrading and maintenance of existing jetties;
  • Priority repairs to the existing breakwater; and
  • Priority maintenance to existing buildings and demolition of 'Building B'.

  Reference group

The Two Rocks Marina Reference Group has been established to look at the long-term vision for the facility, with a view to creating local jobs. The Reference Group will play a key role in ensuring community and user group interests and concerns are identified and addressed.

Chaired by the Mayor of the City of Wanneroo Tracey Roberts, the majority of the 14 member Two Rocks Marina Reference Group represent the community, business interests, landowners and facility user groups.

The Reference Group Membership comprises:

  • Business Representative - John Young.
  • Business Representative - Mark Weir.
  • Business Representative - Michael Bower.
  • Business Representative - Nick Perignon.
  • City of Wanneroo Chief Executive Officer.
  • City of Wanneroo Elected Member, Natalie Sangalli.
  • Community - Brad Lynton.
  • Community - Jenny Butler.
  • Community Group - Elysia Regan, Two Rocks Beach Action Group.
  • Department of Planning Lands and Heritage Director North Metropolitan.
  • Department of Transport Director Maritime Planning.
  • Department of Transport Manager Coastal Management.
  • User Group - Bill White, Two Rocks Volunteer Marine Sea Rescue.
  • User Group - Commodore Wayne Hartas, Sun City Yacht Club.
  • User Group - Mick Bowra, Two Rocks Boat Lifter.
  • User Group - Peter Russell, Penholder.

Facility manager, the Department of Transport, will coordinate the group.

Minutes from Meetings that have been ratified by the Reference Group Members can be found below. All presentations given can also be found below.

Ongoing updates on Reference Group meetings and planned works will be provided via this web page, and you can also register for updates via the email address below:

PROJ_P_TwoRocksProject_RefGrp_Meet4_Presentation.pdf icon Two Rocks Marina Reference Group: Meeting No. 4 - Presentation summary Kb
PROJ_P_TwoRocksProject_RefGrp_Meet3_Presentation.pdf icon Two Rocks Marina Reference Group: Meeting No. 3 - Presentation summary Kb
PROJ_P_TwoRocksProject_RefGrp_Meet3_Minutes.pdf icon Two Rocks Marina Reference Group: Meeting No. 3 - Minutes Kb
PROJ_P_TwoRocksProject_RefGrp_Meet2_Presentation.pdf icon Two Rocks Marina Reference Group: Meeting No. 2 - Presentation summary Kb
PROJ_P_TwoRocksProject_RefGrp_Meet2_Minutes.pdf icon Two Rocks Marina Reference Group: Meeting No. 2 - Minutes Kb
PROJ_P_TwoRocksProject_RefGrp_Meet1_Presentation.pdf icon Two Rocks Marina Reference Group: Meeting No. 1 - Presentation summary Kb
PROJ_P_TwoRocksProject_RefGrp_Meet1_minutes.pdf icon Two Rocks Marina Reference Group: Meeting No. 1 - Minutes Kb

  Coastal infrastructure project contact list

Service Type Suburb Business Name Phone number Phone number (secondary) Fax Pre-booking required Business Hours Email Street address Postal address Business Type Comments
Coastal infrastructure project Bandy Creek Weir (Coastal infrastructure project) (08) 9435 7833 No Monday to Friday 8:00 am until 5:00 pm. (excludes public holidays) bandycreekweir@transport.wa.gov.au WA 6450 WA Department of Transport
Coastal infrastructure project Beadon Creek (Onslow) maritime facility (Coastal infrastructure project) (08) 9435 7676 No Monday to Friday 8:00 am until 5:00 pm. (excludes public holidays) WA Department of Transport Regional Facilities Coordinator
Coastal infrastructure project Broome Boating Facility (Coastal infrastructure project) (08) 9216 8240 No Monday to Friday 8:00 am until 5:00 pm. (excludes public holidays) james.holder@transport.wa.gov.au WA WA Department of Transport James Holder, Manager Maritime Projects
Coastal infrastructure project Burswood Public Jetty (Coastal infrastructure project) (08) 9435 7613 No Monday to Friday 8:00 am until 5:00 pm. (excludes public holidays) michael.maslin@transport.wa.gov.au WA WA Department of Transport Michael Maslin, Project Manager
Coastal infrastructure project Casuarina Boat Harbour (Coastal infrastructure project) (08) 9435 7539 No Monday to Friday 8:00 am until 5:00 pm. (excludes public holidays) casuarinaharbourupgrade@transport.wa.gov.au WA WA Department of Transport Dilhan Wijesinghe, Project Manager
Coastal infrastructure project Denham Maritime Facility upgrades (Coastal infrastructure project) (08) 9435 7613 No denhamforeshore.info@transport.wa.gov.au WA WA Department of Transport Michael Maslin, Project Manager
Coastal infrastructure project Fishery Beach (Bremer Bay) boat ramp protection (Coastal infrastructure project) (08) 9435 7613 No Monday to Friday 8:00 am until 5:00 pm. (excludes public holidays) michael.maslin@transport.wa.gov.au WA WA Department of Transport Michael Maslin, Project Manager
Coastal infrastructure project Fremantle FBH Jetty 2 redevelopment (Coastal infrastructure project) (08) 9435 7546 No Monday to Friday 8:00 am until 5:00 pm. (excludes public holidays) francois.sauzier@transport.wa.gov.au WA WA Department of Transport Francois Sauzier, Project Manager
Coastal infrastructure project Hillarys Boat Harbour upgrade (Coastal infrastructure project) (08) 9435 7546 No Monday to Friday 8:00 am until 5:00 pm. (excludes public holidays) francois.sauzier@transport.wa.gov.au WA WA Department of Transport Francois Sauzier, Project Manager
Coastal infrastructure project Jurien Bay Boat Harbour (Coastal infrastructure project) (08) 9435 7559 No Monday to Friday 8:00 am until 5:00 pm. (excludes public holidays) jurienboatharbour.info@transport.wa.gov.au WA WA Department of Transport James Holder, Manager Maritime Projects
Coastal infrastructure project Port Geographe reconfiguration (Coastal infrastructure project) 1300 660 815 No Monday to Friday 8:00 am until 5:00 pm. (excludes public holidays) portgeographe.Info@transport.wa.gov.au P.O. Box Box C102, Perth WA 6839 Department of Transport Justin Fifield, Project Manager
Coastal infrastructure project Two Rocks Marina upgrade (Coastal infrastructure project) (08) 9435 7833 No Monday to Friday 8:00 am until 5:00 pm. (excludes public holidays) tworocksmarina@transport.wa.gov.au WA WA Department of Transport Anna Kelderman, Project Manager

  Two Rocks Marina project: Documents

MAC_P_Boat_Harbour_Loc_NthMetro.pdf icon Boat Harbour Locations North Metropolitan Region Kb
PROJ_P_TwoRocksProject_RampUltimateConcept.pdf icon Two Rocks Marina: 2016 boat ramp upgrade and boat pontoon plan Kb
PROJ_P_TwoRocksProject_Existing_Marina.pdf icon Two Rocks Marina: Existing Marina Kb
PROJ_P_TwoRocksProject_ExistingOppConstraintInvegCompleted.pdf icon Two Rocks Marina: Existing opportunities, constraints and investigations completed Kb
PROJ_P_TwoRocksProject_PlanningContextComparisons.pdf icon Two Rocks Marina: Existing planning context and Marina comparisons Kb
PROJ_P_TwoRocksProject_Planned_6M_Upgrade_2017_19.pdf icon Two Rocks Marina: Planned $6 million upgrade 2017-19 (Updated June 2018) Kb
PROJ_P_TwoRocksProject_FAQ_Upgrade.pdf icon Two Rocks Marina: Upgrade (Frequently Asked Questions) Kb

 

Page last updated: Thu Jul 26 2018 12:38:43 PM