Hillarys Boat Harbour upgrade
Project status
Completed: The project was undertaken by Shorewater Marine and was completed in May 2019.
03/09/2014: Upgrades at Hillarys Boat Harbour completed |
---|
Replacement of B and C Jetties at Hillarys Boat Harbour
Work to replace B and C jetties at Hillarys Boat Harbour was successfully completed in May 2019 by Shorewater Marine Pty Ltd and the Department of Transport.
The replacement of jetties B and C was part of the Department's ongoing pen replacement program for Hillarys Boat Harbour and followed the $3.5m replacement of jetties K and L in 2014, which saw the delivery of 107 floating pens.
New B0, B and C jetties have been constructed with a new floating pen system that meets high design standards with a total of 91 new pens. The new pen system also improves safety and amenities for penholders and reduces ongoing maintenance costs.
North East car park extension
Work on the $1.2 million extension of the northern car park at Hillarys Boat Harbour to add extra bays to the popular destination has been completed.
The extension of the north east car-park provides an additional 65 car parking bays to help alleviate parking congestion during peak usage periods.
The Scope of Works for Contract was as follows:
- Removal of existing landscaping from inside eastern boundary of the Boat Harbour.
- Removal of existing fencing along the eastern boundary of the Boat Harbour.
- Removal of existing shared use path from inside Boat Harbour boundary.
- Provide additional row of car parking bays adjoining existing bays to the east of the car park.
- Supply and installation of storm water drainage infrastructure.
- Landscaping and vegetation for reinstatement.
- Realignment of existing principal shared path (PSP).
- Install security lighting.
- Construct new car park pavement.
- Provide parking islands.
- Provide traffic island humps.
- Install pavement markings.
- Installation and relocation of services.
- Provision for future CCTV network (conduits and pits).
- Disposal of excess and /or unsuitable material.
- Disposal of redundant material.
The project was undertaken by Transfield Services.
Hillarys Boat Harbour: Proposed North East car park extension | Kb |
---|
Replacement of K and L jetties at Hillarys Boat Harbour
Work to replace the K and L jetties at Hillarys Boat Harbour is complete.
The project was part of the Department's ongoing pen replacement program for the Harbour and K and L jetties were the next pen system scheduled to be replaced. The replacement of the pen system improves safety and amenities for penholders and reduces ongoing maintenance costs.
The existing K and L jetties were replaced with a secure floating pen system that meets high design standards. The new systems saw the delivery of 107 pens and can accommodate vessels up to 15 metres.
The $3.5 million project was undertaken by Engineered Water System and was completed in August 2014.
Hillarys Boat Harbour: Concept image for replacement K and L jetties | Kb |
---|